Planning Time Fence 

Use

You can protect procurement proposals from any automatic changes to master schedule items in the near future by using the planning time fence. Within the planning time fence, the system does not automatically change procurement proposals during the planning run. That is particularly useful for MPS.

You can define the planning time fence either material-specific or per MRP group. The material-specific setting overwrites the MRP group setting.

All procurement proposal types are firmed within the planning time fence:

Prerequisites

When specifying the planning time fence, you should bear in mind the maximum lead time of the materials.

Features

Outside of the planning time fence, procurement proposals are created as usual in the planning run. When these procurement proposals move into the planning time fence, they are firmed automatically depending on the setting of the firming type.

The system always calculates the end date of the planning time fence dynamically starting from the planning date.