Carry Out Total Planning Online
This takes you to the initial screen for the total planning run.
The creation indicator for purchase requisitions is only valid if the MRP group does not override it. The creation indicator for scheduling agreement schedule lines is only valid if the MRP group or the plant entry in Customizing does not override it (see Creation Indicators in the Initial Screen and the MRP Group ).
If you want to save the parameters set in the initial screen, for the following total planning, choose Settings ® Save. The parameters saved become the default for each following planning run.
The system displays the long texts explaining the settings selected.
Result
The system carries out total planning for the plant selected or for the scope of planning you have defined. The individual plants or MRP areas are planned in the sequence defined.
When you have completed the planning run you receive statistics with information on the scope of planning, exceptional situations and terminations. You can also see how much time is required for the planning run in total and for planning the individual materials.
To limit the scope of these statistics you can set the number of materials used, in Customizing for MRP under Activate runtime statistics.
If you carry out the total planning in the background, you can print these statistics.
If you have selected the field Display material list in the initial screen of the planning run, the list of the materials planned is displayed above the statistics. If you position the cursor on a specific material in the list and choose MRP list or Stock/ requirements list, this takes you directly to the appropriate list and from there you can test the planning result.