Production in Alternative Plant
Implementation Options
You can define that a particular product is to be produced in an alternative plant (that is, the production plant) from the planning plant. The planning of the product is carried out in the planning plant but it is actually produced in the production plant. The product's BOM is created in the production plant.
Prerequisites
Process Flow
The following graphic shows the steps involved in producing material in another plant:
The following is to be taken into account for the scheduling of the planned orders in the planning plant:
The system uses the in-house production times and scheduling margin key entered in the material master record for the planning plant to determine the basic dates.
If MRP is carried out using lead time scheduling via the routing, the routing and scheduling margin key in the production plant are the basis of the production date calculation in.
If you have defined that the basic dates are to be adjusted for the production dates in lead time scheduling (Customizing, IMG activity Define scheduling parameters for planned orders) the system calculates the basic date by adding the production finish date and the float after production. The system uses the production start date minus float before production as the order start date. The system determines the float before production and the float after production from the scheduling margin key in the material master record for the production plant.