Example of Forward Scheduling for External Procurement
Example Data
Material shortage date |
01.08 (Friday) |
Planned delivery time of the material |
10 days (calendar days) |
Processing time for purchasing |
1 day (workdays) |
Goods receipt processing time |
2 days (workdays) |
Opening period |
10 days (workdays) |
Workdays = Monday to Friday, no bank holiday |
Scheduling
01.08. (Friday) plus 1 workday + 10 calendar days = 14.08. (Thursday)
14.08. (Thursday) plus 2 workdays = 18.08. (Monday)