Implementation Options
The basic dates determine the outermost time limits for production. During material requirements planning and forecast-based planning, the system calculates the order start and finish dates in addition to the order opening date of the planned order.
Prerequisites
The opening period is the time required by the MRP controller to convert the planned orders into purchase requisitions. It is only taken into account with backward scheduling.
Process Flow
If you do not want the system to switch to forward scheduling automatically, you can specify per plant in Customizing for MRP, in the IMG activity Parameters for determining the basic dates that the system is to continue the backward scheduling calculation even if the resulting start date lies in the past.