Scheduling: In-House Production 

Process Flow

  1. The system calculates the basic dates for planned orders.
  2. The basic dates are the order finish date and the order start date. The order finish date determines the latest possible date by which production has to be finished and the order start date determines the earliest possible start of production.

    Basic dates are calculated automatically during every planning run.

  3. The system calculates the exact production dates (lead time scheduling).

The production dates are the production start date and the production finish date.

Additionally, capacity requirements are created during lead time scheduling.

Lead time scheduling is only carried out on request.