Gross Requirements Planning 

Use

Gross requirements planning is initiated by planning with the planning strategy Make-to-stock prod./gross reqmts plng. Planned independent requirements, created using this requirements type, are not compared with warehouse stock in material requirements planning. The system only checks against the expected receipt quantity (from planned orders, purchase requisitions, and so on). This means that a mandatory master plan can be stored in the system.

The gross requirements plan is displayed in a separate segment in the MRP list as well as in the stock/requirements list.

Prerequisites

Features

Available stock is calculated as follows:

A shortage occurs if available stock is negative, that is, the requirement quantity is greater than expected receipts.

The system specifies the date of the issue (for example, customer requirement, planned independent requirement, reservation, forecast requirement) as the requirements date.