Starting from the MRP menu choose Planning ® Planning file entry ® Display.
The initial screen for displaying planning file entries now appears.
Enter your selection criteria:
If you leave the material, MRP area, plant and low-level code fields blank, the system selects all materials in all MRP areas and all plants.
Choose .
The system displays a list of all the materials that fulfill your selection criteria.
- The record type of the planning file entry is given in column RT. MRP materials are automatically provided with a B and phantom assemblies with a D.
- In the low-level code column, you can see the respective low-level code of the material. In the material master record, each material is allocated one low-level code (field L.Lvl Code) which is determined by the bill of material (BOM) management program. You can also display the low-level code in the material master (Additional data, ).
If a material does not appear in a bill of material, the system will automatically allocate the highest level (999).
- In the MPS item column, the indicator for a master schedule item is set.
- If the Net change planning indicator is set for a material then it is included in the net change planning run.
- If the Net change planning horizon indicator is set for a material then this material is included in the net change planning in the planning horizon.
- If you set the BOM explosion indicator, then available planned orders are taken over but the BOM is re-exploded and the routing re-released.
- If you set the Reset order proposal indicator, then planning dates that may be available are always deleted and recreated.
- Choose Statistics.
A window with statistical data appears. Here you see how many materials have been selected in total and how many of these exist for each of the indicators mentioned above.