Implementation Options
Materials may appear in several products and in several production levels of a product. The low-level code represents the lowest level of usage of a material within all product structures.
It determines the sequence in which the materials are planned. The system plans materials with the low-level code 0 first and then those with 1 and so on. The lower the low-level code is, the higher the number assigned to the level.
Prerequisites
You have created BOMs for the materials that you want to plan.
Process Flow
Result
The low-level code is stored in the BOM management program in the material master (Additional data,
) and is entered in the planning file.