Planning Run Type 

Use

The planning run type determines which materials are to be planned:

The system plans all the materials that are contained in the planning file

The system only plans materials that have undergone a change relevant to MRP since the last planning run

You choose the required planning run type in the initial screen of the planning run (see Planning Run Type in Initial Screen).

Features

Net Change Planning (NETCH)

In net change planning only those materials are planned for which the net change planning indicator in the planning file has been set as a planning file entry. The system usually sets the indicator automatically as soon as a change is made to the material that is relevant to MRP.

The following changes cause an entry in the planning file to be made:

If you have changed the settings of an MRP type, a lot-sizing procedure or a purchasing department processing time in Customizing, the materials that are affected by these changes thus have no planning file entry and are not included automatically in the net change planning. To enable the changes made to take effect, you choose regenerative planning in the initial screen of the planning run or make an entry manually in the planning file.

Net change planning in the planning horizon (NETPL)

You can also use a planning horizon to further limit the scope of the planning run. In "net change planning in the planning horizon", the system only plans materials that have undergone a change that is relevant to the planning run within the period which you defined as the planning horizon. The system sets the net change planning horizon indicator automatically for these materials.

Activities

If a termination occurs when planning a material, the indicators for this material remain in the planning file so that the material is planned again in the following net change planning run. However, depending on the error, you can manually delete the indicators in Customizing for MRP in the IMG activity Define Error Processing in the Planning Run if necessary (for example, if a certain material is not available in the planning plant). This means that you can avoid a situation where materials are pointlessly planned again and again.