You can maintain the quota file in Purchasing or MRP. In this section, a description is given of how to maintain this file from Material Requirements Planning.
The initial screen for maintaining quota appears.
The header screen for maintaining quotas appears.
You can only define continuous validity periods for one material. In the first interval, the system sets the current date in the Valid from field. The Valid from dates of the other intervals are set continuously so that the day after the end date of the last quota item is set as the start date for the next item.
The item screen now appears.
Allocating the source of supply to the quota item determines the procurement type that the procurement proposal receives. Therefore, you can specify via the quota arrangement that, for example, 60% of a material is produced in-house and the other 40% is procured externally.