Changing the Planning Calendar 

  1. Starting from the MRP menu choose Master data ® Planning calendar ® Change periods.
  2. The initial screen for planning calendar maintenance now appears.

  3. Enter the plant for which the planning calendar is to be valid.
  4. Choose Calendar overview or Calendar no longer valid.
  5. Calendar overview: the system displays all the planning calendars available in the system.

    Calendar no longer valid: the system displays all calendars, for which the minimum period independent of the Valid to date has been exceeded, and suggests them for reprocessing.

  6. Select one or more planning calendars and choose .

The first selected planning calendar now appears. Here, you can carry out the necessary changes.

Function

Menu path

What you should know

Calculating new periods

Change calculation rule

Proceed as described in Creating Planning Calendars with Calculation Rule.

Adding periods

 Periods

Choose New entries.

Inserting periods

 Periods

Position the cursor on the line where you want to insert a new period.

Choose Edit ® Insert and enter a new period end and a new period start.

Changing periods

 Periods

Overwrite the From date or the To date.

Deleting periods

 Periods

Position the cursor on the period that you want to delete.

Choose Edit ® Delete.

Fixing periods

 Periods

Select the fixing indicator for the period(s) to be protected.

Fixed periods are not changed if you instruct the system to automatically calculate new periods.

  1. Save your entries.

If you selected several calendars in the overview, the system now automatically displays the next planning calendar that you selected.