Sending the PI Sheet 

Use

The control recipes for the process orders of material N-2100 and N-2000 are sent to the control recipe destination TB (tablet production). The following functions are performed: send PI sheet, update control recipe status.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    From the Production - Process node, choose Process Management ® Control Recipe ® Control Recipe Monitor

    Transaction Code

    CO53

  3. Enter the following data:
  4. Field

    Data

    Plant

    1100

    Status

    Select all

    Mode

    Select No test

    Process order

    No entry

  5. Use the value help to select destination address GRP. TAB.
  6. Choose .
  7. Choose Display.
  8. The Control Recipe Monitor: Overview screen appears.

  9. Choose .
  10. Choose Send.
  11. The system sends the control recipes to the relevant destinations.

  12. To check the status, choose .
  13. Choose until the overview tree appears.