Changing a Production Order 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Order node, choose Change

    Transaction Code

    CO02

  3. Enter the following data:
  4. Field

    Data

    Order

    Number of the production order you have created

  5. Choose .
  6. Choose Header ® Settlement rule
  7. Distribute the order costs as follows (in percentages):
  8. Receiver

    Equivalence number

    Order no. For item 0001

    78

    Order no. For item 0002

    10

    Order no. For item 0003

    10

    Order no. For item 0004

    2

    The system collects the total costs of the production order at the header level and distributes them to individual co-products according to the equivalence numbers.

  9. Choose .
  10. Choose to display the goods receipt data and settlement rule for the order items.
  11. Select one of the co-products and choose to display further details.
  12. Write down the movement type.

  13. Choose .
  14. Select items 0010 through 0060, then choose .
  15. Deselect the co-product first.

  16. In the General indicators section, set the Backflushing indicator.
  17. Choose .
  18. Set the Backflushing indicator for all components you have selected.
  19. Choose to confirm the information message that is displayed when you reach the last component selected.

  20. Choose until you get to the Production Order: Header screen.
  21. Choose .
  22. Choose .
  23. Choose until the overview tree appears.