Use
In the R/3 System, you can use the CCMS DBA Planning Calendar to schedule backups of the database or transaction log. SAP recommends that you use the Planning Calendar to schedule all regular backups that are part of your overall backup strategy. The calendar offers two approaches:

A backup that has been scheduled in the CCMS Planning Calendar is displayed in the Job List of the Enterprise Manager. However, a backup that has been scheduled in the Enterprise Manager is not visible in the Planning Calendar.
Procedure
Scheduling Backups Manually
The Planning Calendar is displayed.
If actions have already been scheduled on the chosen day, these are displayed.
If not, a list of the actions available for scheduling is displayed.
Entire Database
Dialog Box |
Entry |
Database Selection |
Choose the databases you wish to back up. |
Backup Device Selection |
Select the backup device that the backup will be written to. Generally the default device R3DUMP0 is the correct entry here. |
Details for Tapes |
Unload Tape Initialize Tape Verify backup Format tape Expiration Period |
Transaction Log
Dialog Box |
Entry |
Backup Device Selection |
Select the device that the backup will be written to. Generally the default device |
Log Backup Tape Options |
Accept the expiration period of 28 days, if you are performing the backup in the framework of the overall backup strategy recommended by SAP. Verify backup If you want to write multiple log backups of one day to a single tape, set the following options: |

If you assume that the backup of the database will not fit on one tape, you need to perform a parallel backup. Prerequisite is that you have installed a second tape device. Select both available devices in the Backup Device dialog box. The backup will automatically be written to both selected tapes in parallel.
See also:
Backup Device ManagementTo find out which label has been assigned to a volume, double-click on the header of the day when the backup is scheduled. In the window that appears, select the backup in question and choose Volumes Needed.
The backup device and the name assigned to the tape volume are displayed.

If you wish to modify a backup scheduled in the Planning Calendar, do so within the Planning Calendar and not within the Enterprise Manager. Modifications made within the Enterprise Manager are not visible within the R/3 Calendar.
Scheduling Backups with Planning Patterns
The Planning Calendar is displayed.
A dialog box with a planning pattern appears.
5 workdays, DB backup + hourly log backup (8am - 6pm) + Monthly Check DB

The planning pattern will only be applied, if there are no collisions with existing tasks scheduled at the same time.
All the backups that are scheduled are subsequently displayed in the calendar.
A sequence of dialog boxes appears showing the parameter values that have been set. Confirm each dialog box with OK in order to proceed to the next one.
For more information, see