Use
You now execute multi-level requirements planning for the finished product N-2000, and then check the results. You check whether the sales plan is transferred correctly to demand management.
Procedure
Menu Path |
From the Production - Process node, choose MRP ® Evaluations ® Stock/Requirements List |
Transaction Code |
MD04; MD02 |
Field |
Data |
Plant |
1100 |
Product group |
Select |
Product group description (field after the Product group radio button) |
N-PG2000 |
Now, carry out MRP for material N-2000.
Field |
Data |
Material |
N-2000 |
Plant |
1100 |
Processing key |
NETCH |
Create purchase req. |
2 |
Delivery schedules |
3 |
Create MRP list |
1 |
Planning mode |
3 |
Scheduling |
1 |
Also plan unchanged components |
Select |
Display material list |
Select |
To skip the information message, simply choose
.
The statistics overview appears.
You can see the overview of the planning results.
You see the planning results based on the planned orders generated during MRP for the finished product.
In the dialog box, choose Yes.