Use
You use this measurement method to determine actual values for activities whose progress is mentioned in terms of internal activities.
Prerequisite
The activities or activity elements for which you want to use this technique must be confirmed.
Features
When you use this measurement technique, the degree of processing from the confirmation becomes the percentage of completion.
You can maintain the POC manually in the confirmation for the activity/activity elements or have the system calculate it from the data in the confirmation.
See
Calculation of Actual Work, Remaining Work and the Degree of Processing .
Example
You confirm activity 0010 "Assembly" with a 20% degree of processing. This means that the actual POC for the activity is also 20%.