Estimates 

Use

Using this method involves making a subjective assessment of the project degree of completion. The method is schedule-based. This measuring technique is based on scheduling.

You use this technique when no other, objective method is available. The work package duration for this technique should be more than three months.

Prerequisite

The following table gives you an overview of the menu paths to choose so that you can maintain data you need for your estimates:

Object

Maintain estimate data by choosing...

Projects in structure planning

Details ® General, then Progress tab page, then choose Estimated value

Projects in the project planning board

Details ® Detailed information on object, then Progress tab page, then choose Estimated value

WBS elements

Details ® General, then Progress tab page, then choose Estimated value

Activity or activity elements

Details ® Activity/element ® General, then Progress tab page, then choose Estimated value

In addition, you can also enter a measurement method for estimates and a maximum percentage of completion in Project System customizing.

A maximum POC prevents an overestimate of completion such as occurs when tasks are "almost finished" (also called the "90% syndrome"). As long as the task has not been completed, that is, no actual finish date has been entered, the system will not allow you to have an actual POC that is higher than the maximum POC.

We recommend a maximum POC of 80% for the actual POC estimate.

Features

In this measurement method, the system adopts the percentage entered manually as the POC for the specified period.

You always enter the cumulative estimate. The values are not regarded as additive.

Example

Plan Dates

Estimated Values

Planned POC

05.99

10%

10%

06.99

30%

30%

07.99

100%

100%