When Are Project Versions Created?  

Project versions are:

Time-Dependent

At a particular point in time, you create a project version manually. You can do this in the WBS, network, or information system.

Status-Dependent

The system automatically creates a project version when there is a system and/or user status change in the selected objects. You define the user/system statuses which trigger creation of project versions in Project System customizing.