Displaying Postponement of Planned Dates (Optional) 

  1. Use the following procedure to call the transaction:
  2. Menu Path

    From the Maintenance Planning node, choose Maintenance Plans ® Display.

    Transaction

    IP03

    The system defaults the number of the last maintenance plan you processed.

  3. Choose .
  4. Choose the Maintenance Plan Schedule Calls tab page.
  5. Make sure you are at the top of the list.

  6. Select the first date (Status: New start, complete) and choose .
  7. Choose .
  8. Check that the subsequent date is postponed by the number of days that the completion confirmation is late. You can see this in the Postponement field.

  9. Choose .
  10. Choose to return to the overview tree.