Preference Determination for Bills of Material with Alternative Items 
Use
After exploding the bill of material, the system checks the components for alternative items. For each new preference zone, the system must check which alternative items can be used for preference determination. As different preference rules are valid in each preference zone, different alternative items may be selected in each preference zone. The system always selects the item which has the worst effect on the preference price of the main part. Starting with the lowest bill of material (BOM) level, the system checks which alternative items qualify for preference.
Features
Assembly with Exploded BOM
If an alternative item is an assembly and cannot be exploded because of a selection parameter, each alternative item is treated as a main part. This means that preference determination is performed for the material of the alternative item. However, which procedures and rules are selected depend on the commodity code of the main part.
In-house produced components qualify for preference if they have been included based on selection data in the most recent preference determination without changing the database. Preference also requires that a valid preference ID and a preference price could be determined for them.
Assembly Without Exploded BOM
If an alternative item is an assembly and cannot be further exploded based on the selection parameter, the system presumes that preference determination has already been performed for the alternative item.
In-house produced components qualify for preference if the following conditions are true:
Externally Procured Components
Externally procured components with a valid vendor declaration qualify for preference.