Create System Conditions or Operating Conditions

In this step, you can define the possible asset conditions.

Effects on the capacity load in production

In the functional location and equipment reference objects, you have the option of defining a production work center.

If your maintenance tasks should affect the capacities of the production work center, you must select the field 'Document by PM' in this setting. As a result, a capacity load for the production work center is created by the maintenance order.

The capacity loads for maintenance work centers are not affected, but are subject to the normal capacity load logic.

Note

You can enter a system condition in the maintenance order for every operation. Using this system condition, you can determine whether the operation must be carried out in production or when the system is shut down, for example.