Working with Planning Result and Planning Situation
In the display of the planning result or the planning situation, you have the following processing options:
Function |
How to call up function |
What you should know |
Open and close hierarchy elements |
Click on an element that is highlighted in color |
The level directly below the element is opened or closed. On the lowest level, a detail dialog box with a list of all related MRP elements appears. |
Display MRP elements for a particular period |
Click on a period that is highlighted in color (column header) |
|
Scroll into the past or the future |
, , , |
You can scroll through columns or pages. |
Change the period display |
View ® Time axis ® <required period> |
As standard, the evaluation is displayed in monthly periods. |
Change unit of measure used for display |
View ® Unit ® Unit of measure |
In the SAP Standard System, the quantities of the MRP elements in the display are displayed in the base unit of measure. If you have maintained alternative units of measure in the material master (for example output or order unit) or if the unit of measure can be converted into another unit (for example kilo into tons), the elements can also be displayed in these alternative units of measure. |
Choose value display instead of quantity display |
View ® Unit ® Valuation price |
By choosing View ® Unit ® Price unit, you can select other price types and currencies. |
Display MRP segments |
Edit ® Choose segment |
The system displays data only for the segment selected. The system shows which segment it is in the header of the evaluation. |
Display and change MRP element |
Click on the MRP element and then or in the detail dialog box |
|
Convert MRP element |
Click on the MRP element and then the appropriate function in the detail dialog box |
|
Display pegged requirements or order report |
Click on the MRP element and then or in the detail dialog box |
For more information, see Pegged Requirements and Order Report. |
Display warehouse stock (only for planning situation) |
Goto ® Warehouse stock |
|
Display the composition of a hierarchy element |
Position the cursor next to a hierarchy element, and choose Goto ® Evaluation Profile. |
A list of MRP elements that belong to the hierarchy element selected appears. |
Save the evaluation layout |
Planning situation or Planning result ® Save layout |
If you defined an individual period split in Customizing, you can enter this period split here. The same layout appears again the next time that you access the evaluation. |
Set processing indicator for planning result |
Edit ® Mark as processed |
The processing indicator is not visible in the planning result itself. |
Delete planning result |
Planning result ® Delete document |
If you do not delete the planning result manually, it remains in the system until a new planning result is created by a subsequent planning run. |
Print evaluation |