Perform Setup -
Production
In this step you can initialize the information
structures from the Shop Floor Information System.
The following report helps you to do
this:
It reads the
production orders and triggers the statistics update of
these orders in accordance with the selection you made in the selection
screen.
In this process,
only the production orders in the system are processed and
not those that have already been archived.
Application-specific selection parameters
Here you specify the
key of the
plants to which the setup of statistical data
applies.
Here you specify the
numbers of the
MRP
controllers or the MRP controller groups which are to be included
in the statistical setup.
Here, you specify
the order numbers which are to be included in the statistical
setup.
Here, you specify
the creation date of the production orders to which the statistical setup
applies.
If you set this
indicator, the system carries out a check via the information structure S021
(production order) to see whether a production order was already updated for
the specified version.
Updating is only
carried out if this is not the case.
Note
In the standard R/3
system, this indicator is not set.
- Enhanced setup of statistical
data
Some communication
structures must be stored in the Shop Floor Information System for technical
reasons. This applies to release versions and costs.
If you use the
indicator "Enhanced setup", the respective communication structures will be
set up.
The note also
applies to this (see below), which states that the quality of the setup data
is generally worse than the quality of the data from online
updating.
You can use report
RMCFCSCP to copy the communication structures that were
created by the enhanced statistical setup.
Caution
You can perform a
statistical setup for two basic reasons:
In the first case,
you wish to perform a statistical setup of all the selected data because the
statistics update was switched off, for example, or because there were errors
in the statistical data. In this case, it is recommended to execute an
enhanced statistical setup.
In the second case,
you want to fill a new information structure with statistical data. In this
case, you should not execute an enhanced statistical
setup.
This report has
essentially the same functionality as the report
RMCSISCP.
Both of these
reports enable you to copy or delete versions as part of the statistical
setup.
In contrast to
report RMCVISCP, the selection criterion "Date" is not not included in the
report RMCFCSCP.
Instead, the report
RMCFCSCP uses the selection criterion Order
. Here, you need to specify the order numbers of the production orders which
determine the restrictions to be made.
Note
Due to technical reasons involving data, the
calculated costs cannot be reconstructed according to specific work centers
because this allocation is only temporary. This is not relevant to the
production cost analysis (S027) since the work center is not a characteristic
in this standard analysis.