Cost Proportionality 

Use

This measurement technique is suitable for work packages where costs and services have a constant relationship.

Prerequisites

Costs must have been planned in the object, or actual costs posted to it, by period.

The system does not take account of costs from hierarchy planning in the WBS element.

Features

The system determines the percentage of completion (POC) for a period from the ratio of planned or actual costs to the overall planned costs. The system determines the planned or actual POC as follows:

BCWS = Planned costs/overall costs * 100

Actual EV = Actual costs/overall costs * 100

The planned costs are the cumulative planned costs up to the time of the calculation. The overall planned costs are the cumulative planned costs over the duration of the work package. You use the progress version to stipulate which cost plan the system uses.

Example

A work package has overall costs of $100,000.

The table shows how the POC is determined with reference to the overall costs.

Period

1

2

3

Planned costs

10,000

50,000

100,000

Planned POC

10%

50%

100%

Actual costs

5,000

30,000

90,000

Actual POC

5%

30%

90%