Show TOC

Define Checking Control

In this work step, you define the check control. The checking rule together with the checking group specify the scope of the check.

You can make the checking rule as well as the actual check itself dependent on the following parameters:

The operation can have the following characteristics:

Control parameters for the operation 'create'

In addition to this, you can specify whether a planned order can be converted to a production order or process order using collective conversion in the case of:

'Release' control parameters for operation

In addition, you can control whether an order can be released in the case of

Actions

Define the following:

Maintenance orders (PM)

The automatic check at time 1 (create), is not executed for maintenance orders (PM).

You can only carry out the check manually before you have released your maintenance orders.

The automatic check at time 2 (release) is executed if it is switched on. (See "no check" switch).

Notes

on capacity availability check

If you want capacity availability to be checked automatically when the status created or released is set, you cannot set the indicator no check.

If you do not maintain an internal overall profile in the field CapAvailOverProf , the overall profile SAPSFCG013 will be used for the capacity requirements check. The period split is predefined as week in the period profile.

You can use the indicator release to determine how, if at all, the order is released in the case of capacity shortfall: