Show TOC

material provision indicators

Definition

This key indicates that the BOM item is subject to material provision.

Use

In a BOM explosion , you can use this indicator to restrict the items selected.

There are two types of material provision:

Dependencies

This indicator controls MRP. Only maintain this indicator for a material component if the material master record of the header material supports subcontracting (Special procurement field).
The special procurement key for subcontracting means that all components of the BOM are provided free of charge to a subcontractor for further processing. The items are copied to a subcontract order.
This indicator is not currently active.