Procedure
The operations overview of the routing screen appears for your production lot.
The table shows which screen appears.
Navigation when calling up the material component overview
If you have created the following for the production lot |
The following screen appears: |
WBS BOM |
Material Component Overview |
No WBS BOM, but exactly one material BOM for the material of the WBS BOM |
Material Component Overview |
No WBS BOM, but several material BOMs for the material of the WBS BOM |
The Choose alternative BOM dialog box. Select the BOM whose components you would like to assign and choose Select. |
The New allocation. dialog box appears.
– Directly assign the material components
– Assign the material components via the operations list.
To receive a list of the operations to which you can assign the material components, choose Oper./act. list (operation list) in the New allocation dialog box. You then select the operation from the list.
Result
The components are assigned to the operation.