Show TOC

Resource-related billing

Description

Resource-related billing is possible as of Release 3.0 in the following objects:

You can use the costs collected in WBS elements, network activities, and orders for the project as the pricing basis.

Scope of functions

You use CO line items to create the conditions in the billing request, from which you will later generate your billing document. The CO information (such as cost element, CO activity) is coded, using rules defined in Customizing.

Automatic pricing uses the conditions in the sales and distribution (SD) system. This means that rules on prices specific to this contract are taken into account.
The costs from the line items can be used as a basis for pricing.
If you need to evaluate several objects together when billing, you have the option of excluding these objects individually from the current billing run. The expenditure entered in the excluded items is not included in the billing run.
You can change the billing request as follows:
During billing, the system writes a history (document flow). With a history you can see what proportions of an expenditure item have gone into which billing document.
All the selected items are available in one USER exit. The following functions are available:
As part of the billing of actual expenditures, the system can determine the cost of sales in the billing document. As it does so, the expenditure proportions in this billing document are updated as cost of sales.
In addition to the information on costs and activities, you can opt to use statistical key figures to determine the amount to be billed.

Change system parameters in customizing

In the Implementation Guide for the Project System, you must assign activity numbers to the cost elements or cost center/CO activity combinations.

Additional information

Additional information

Further notes

For additional information, refer to the Billing documentation in Sales and Distribution (SD).