Scheduling the Maintenance Plan 

Use

To ensure that a maintenance order is generated at regular intervals, you need to schedule individual maintenance plan calls.

Procedure

  1. Use the following procedure to call the transaction:
  2. Menu Path

    From the Maintenance Planning node, choose Scheduling for Maintenance Plans ® Schedule

    Transaction Code

    IP10

    The system defaults the number of the last maintenance plan you processed.

  3. Choose .
  4. Choose Start.
  5. In the Start of cycle field, you see the date you entered while maintaining the scheduling parameters. In this case, one month ago today.

  6. Choose .
  7. The first scheduled call has the status New start, save to call.

    When you save the maintenance plan scheduling, the system generates the first maintenance order.

  8. Choose .
  9. Choose .