Plan Material Requirements for Sales Order Items 
Use
This procedure describes how you plan material requirements for sales order items when the multi-level BOM for the sales order is finished. It also describes how you then handle order assemblies that have already been planned or have already been manufactured.
Prerequisites
Procedure
The system explodes the multi-level BOM for the sales order item from the lowest level to the highest level and plans all the materials. The system displays the runtime statistics for the planning run.
The system displays the stock/requirements list for the material. The MRP elements are displayed in a separate individual customer segment.
The overview tree is displayed on the left of the screen. Only the material for the sales order item is displayed in the tree.
All the materials that the system planned when it exploded the BOM are displayed hierarchically in the order tree.
Result
The system has planned all levels of the multi-level BOM for the sales order item. At the same time, it has settled any planned independent requirements from assembly planning against the dependent requirements that were transferred from top to bottom in the planning run.