When you upgrade to the next release, table settings are only available in
client 000. To use these settings in other clients, you must copy them. To do
this, proceed as follows:
1. Log onto the system in the client, into
which you want to copy the Project System table settings.
2. For each area within the Project System,
carry out the functions described below.
Remember that the function is executed as soon
as you double click on it.
After the system has finished copying, you will
receive a log in which you can see if the table entries were copied
successfully.
Work breakdown structure and project planning board
Proceed
Network
Proceed
Standard network
Proceed
Cost planning
Proceed
Work center
Proceed
Scheduling
Proceed
Production resources/tools
Proceed
Information system
Proceed
Capacity planning
General Proceed
Object overviews Proceed
Sets Proceed
Capacity leveling
Proceed
Graphic