Menu Path |
From the Information System node, choose Reports on Project Cost Controlling ® Costs ® Plan-Based ® Hierarchical ® Plan/Actual/Variance |
Transaction Code |
S_ALR_87013532 |
Field |
Data |
Database profile |
000000000001 |
Field |
Data |
Project |
Your project |
WBS element |
Empty |
Network/order |
Empty |
You see the overall costs for the project. The planned annual values for the current year and the next year are displayed to the right.
In the Exit Report dialog box, choose Yes.