Display Project Planning 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Information System node, choose Reports on Project Cost Controlling ® Costs ® Plan-Based ® Hierarchical ® Plan/Actual/Variance

    Transaction Code

    S_ALR_87013532

  3. Confirm any dialog boxes that may appear by choosing .
  4. In the Enter Profile dialog box, enter the following data:
  5. Field

    Data

    Database profile

    000000000001

  6. Choose .
  7. Enter the following data:
  8. Field

    Data

    Project

    Your project

    WBS element

    Empty

    Network/order

    Empty

  9. Choose .
  10. You see the overall costs for the project. The planned annual values for the current year and the next year are displayed to the right.

  11. Choose .

In the Exit Report dialog box, choose Yes.