Show TOC
Request For
Budget Change
Use
You can use a request in the Internet for an
order, network, network activity, or a WBS element ( = budget consumer)
budget.
The budget request procedure is as
follows:
- The person entering the data enters the
object, the required budget increase ( = amount), and the currency in the
request form.
- The person making the request may know who is
to approve or process the budget allocation, and can enter this person's name
or let the system determine the name.
- The budget request is forwarded to a person
for approval/processing. An accounting clerk may also be involved in
processing the request in the SAP-R/3-System.
There are twoscenarios
(= 2 web forms):
- Budget request (scenario
SR61)
The form is sent to
a processor, who also changes the budget.
The processor executes the budget transaction in the
SAP-R/3-System.
- Budget request with approval (scenario
SR62)
The form is sent to
someone for approval.
This person must
approve the request, after which it is sent to the processor via workflow
(this is determined using the role), who makes the budget changes in the
SAP-R/3-System.
Note
The person approving
the change can also execute the transaction.
The budgeting currency (group currency, object
currency, or a currency chosen by the user) is determined by the Customizing
in the budget profile.
For the WBS element, the budget managers are
the WBS element manager and the project manager. You can define these in
Customizing.
Effects on
Customizing
The customizing settings for both the scenarios
for budget changes are stored in Customizing for the internal service
request.
For more information on customizing the
internal service request, see the SAP Library under
Cross-Application Components -> Internet / Intranet
Services.