Adjustment Due to Modernization 

Displaying a Construction Measure and a Lease-out

Use

The landlord can pass on a certain percentage of modernization cost (construction costs) to the tenant. You have to create a construction measure, assign planned costs, and the corresponding rental units. In this case, the landlord has installed a new automatic garage door. The costs of this construction is going to be distributed among the three garage spaces that benefit from this modernization. In this section, you will first display the master data of the construction measure and then go into one of the lease-outs to view the adjustment that has resulted from this modernization.

Procedure

  1. Call up the function as follows :

Menu Path

Accounting à Real Estate Management à Rent adjustment à Rent calculation à Construction measure à Construction measure à Display

Transaction

FOMC

  1. Enter the following data:

Field

Data

Modernization measures

GARAGE DOOR

  1. Choose Master data or .

The system displays the plan and the actual data for this project.

  1. Choose Cost distribution.

Here you can see that the rental units 1000 to 1002 from business entity 100 are assigned to this adjustment run. The total cost is distributed by Apport.unit 14 (apportionment unit). 14 stands for distribution by percentage rate.

  1. Choose to return to the Easy Access menu.

Now you will display a lease-out after the basic rent condition has been adjusted by the adjustment method modernization.

  1. Call up the function as follows :

Menu Path

Accounting à Real Estate Management à Rental à Tenant information

Transaction

FOTI0A

  1. Enter the following data:

Field

Data

Key date

[Today’s date]

Company code

3000

Contract

0100.1001.001

  1. Choose .
  2. Choose Extras à Rent Adjustments à Adjustments Made to see that condition Basic Rent has been adjusted with adjustment due to modernization.
  3. Choose to return to the Easy Access menu.

Creating a Construction Measure and Adjusting a Rental Unit

Use

The landlord can pass on a certain percentage of modernization cost (construction costs) to the lease-out(s) or to the rental unit(s). To do this you have to create a construction measure, assign planned costs, and the corresponding rental unit(s). In this case, you have installed a new automatic garage door. Part of the cost of this construction is going to be distributed to the garage space that benefit from this modernization

In this process you will use the rental unit you created in the Master Data section with the usage type Parking space. You will then create a construction measure and apportion a part of the costs to this vacant rental unit. Finally you will simulate and activate the adjustment run.

Procedure

  1. Call up the function as follows :

Menu Path

Accounting à Real Estate Management à Rent adjustment à Rent calculation à Construction measure à Construction measure à Create

Transaction

FOMA

  1. Enter the following data:

Field

Data

Modernization measures

[User-definable entry]

  1. Choose Master data or .
  2. Enter the following data:

Field

Data

Description

[User-definable entry]

Start planned for

02/01/2000 [February 1, 2000]

End planned for

02/15/2000 [February 15, 2000]

Total costs planned

5000

Start on

02/01/2000 [February 1, 2000]

End on

02/17/2000 [February 17, 2000]

Total costs

4756

You have just entered the planning data and the actual data for this modernization project. In reality you would most likely enter these two sets of information at different points in time.

  1. Choose Assign RU.
  2. Enter the following data:

Field

Data

BE

[Your business entity number]

frm RU

[You rental unit number with the usage type Parking space]

  1. Choose Cost distribution. Here you can assign cost to specific rental units.
  2. Enter the following data:

Field

Data

Plan.cost share

100

Act.cost share

100

You have assigned $100 worth of the whole cost to this vacant rental unit.

  1. Choose .
  2. Choose to return to the Easy Access menu.

You will now simulate an adjustment run for your construction measure.

  1. Call up the function as follows :

Menu Path

Accounting à Real Estate Management à Rent adjustment à Rent calculation à Construction measure à Simulate

Transaction

FOQU

  1. Under the file tab Selection enter the following data:

Field

Data

User identification

[User definable entry]

Valid-from date

03/01/2000 [March 1, 2000]

Modernization measures

[The measure you created]

Only adjust rental units

[Check-off]

  1. Choose Parameters file tab. Make sure that condition type 10 Basic rent is defaulted in the Condition type field.
  2. Choose .
  3. Choose .

Here you can see the new rent that will be calculated for this rental unit due to the adjustment based on this modernization.

  1. Choose. .
  2. Confirm the dialog box Save Simulation as Update Run with Yes. Whenever a simulation is saved it becomes an update run. For this adjustment to take effect it needs to be activated.
  3. Choose to return to the Easy Access menu.
  4. Call up the function as follows :

Menu Path

Accounting à Real Estate Management à Rent adjustment à Rent calculation à Construction measure à Activate

Transaction

FOQV

  1. Enter the following data:

Field

Data

Company code

3000

User identification

[Your user identification]

Business entity

[Your business entity number]

Rental unit

[Your rental unit with the usage type Parking space]

Adjustment object

Rntal unit [Rental unit]

Follow-up posting due on

03/01/2000 [March 1, 2000]

  1. Choose .
  2. Select your rental unit and choose Activate.
  3. Confirm the dialog box Activate with Yes.
  4. Choose to return to the Easy Access menu.