Releasing Stock from Inspection 
In order to release stock from inspection, you can initiate this action in WM or in IM. For active QM components, you must start this function in Inventory Management. To initiate this action in IM, see
Releasing Stock from Inspection in IM.Processing the Posting Change Notice
To process posting change notices in WM to release goods from inspection
To display a quant list for the selected storage types, choose Quant list (at the bottom of the screen).
The system displays the Quant List screen with two tabs: Available stock and Unavailable for Post.Chge. (If there are no available quants, the system will only display the Stock Overview screen for the material.)
Stock that is unavailable for posting changes is listed in the Unavailable for Post.Chge tab. In this list, a reason that the status cannot be changed (such as, blocked for inspection) is indicated in one of the columns.
For an individual item, you can process the entire quantity or enter a quantity in the Selected quantity column which is less than the quantity shown for an existing quant.
If you do not want to leave the material in the same bin, deselect the Post to same bin column (the system selects this column as a default).
Normally you can enter any quantity in the Selected quantity field. In a bulk storage area that is managed for storage units, if only part of the available quantity in a storage bin is to be processed for a posting change, you must change to the view that displays the stock for each storage unit.
There are two options:
a) You can enter the total Available quantity in the storage bin as the quantity to be converted (Selected quantity).
b) You can select the bulk storage bin and choose the button Display bulk storage quants at the bottom of the screen. The system then displays the stock in the bulk storage bin for each storage unit separately. In this display view of the bulk storage stock, you can select individual quants and process a posting change for only part of a storage unit.
Choose Edit ® Process in foreground or Edit ® Process in background.
For each selected quant the system creates two transfer order items. The first item removes the material to be cleared. This item is always created in the background. The second item replaces the material that was removed.
If the material is to remain in the same bin, the second item is also created in the background. If the material is to be transferred at the same time, you have the option to create the second item in either the foreground or the background.
The system selects the TO item created column to indicate that a transfer order was created.
The system displays a message that identifies the number of the newly created transfer order.
Once you have confirmed the transfer order, the system clears the posting change area (interim storage area).