Copying and Pasting Structure Items 

Use

You can copy structure items, insert them at different levels in the SAP Reference Structure and edit these copies. Copies of structure items can only be added at the same level as the "original" structure item. All subnodes and the following assignments are automatically copied if they were assigned to the original structure item:

Information on the owner, status, and global attributes is not automatically copied. When you copy a structure item, the status is automatically set to Not yet processed.

Procedure

To copy and paste structure items:

  1. Mark a structure item and select . You can copy and paste several structure items at the same time.
  2. Select the position in the structure where you want to insert the copied structure item.
  3. Select a structure item one level above this position. For example, to move a structure item on level to another position, mark the level structure item, below which you want to insert the copied structure item. The copied structure item will then appear at level .

  4. Select . The copied structure item with all its subnodes and assignments appears in the tree structure with the prefix "Copy of".
    Copied structure items are always inserted at the end of a substructure. To rearrange the structure items into an order that makes sense for your project, you can
    change the order of structure items.
  5. You can change copied structure items in the SAP Reference Structure to suit your enterprise requirements. You can:

Result

You have copied and pasted a structure item. Copied structure items are automatically set in scope, when you set the Added structure items indicator under Settings ® Automatically set in scope in the Administration menu. It is possible to delete copied structure items (unlike structure items delivered by SAP).