Displaying Postponements to the Follow-Up Dates
Menu Path |
From the Maintenance Plans node, choose Display. |
Transaction Code |
IP03 |
The system defaults the number of the last maintenance plan you processed.
Check that you are at the very top of the call list.
In the Shift field you can see that the date of the second planning delivery schedule has been shifted.
Result
The change in date is calculated from the start date five weeks previously. The first planned call was set for 30 days after that date. That was one week ago. However, it was not until today that you reported the maintenance order as technically completed. The shift factor of 100% shifts the date by the full value of the delayed completion confirmation.