Capacity Planning Indicator in the Control
Key
Description
In Release 3.0, the functionality of the capacity planning indicator in the
control key has changed:
- Capacity requirement records are only created if you maintain the
indicator.
- You only use the Scheduling indicator to control
whether the activity is to be scheduled.
For capacity planning and scheduling, note:
- If you maintain the Capacity planning indicator,
you should also maintain the Scheduling
indicator.
Change system parameters in customizing
Maintain the scheduling indicator in the corresponding control key:
- Control key standard network: