Generation of Worklist for Planned Maintenance
Scope of Functions
From Release 4.6A, you can generate a worklist for planned maintenance from maintenace planning.
Using the list editing function for notifications ("worklist"), it is
possible to combine several notifications, which have been generated by
maintenance plans, into one order. For example, you can select all the
notifications for a particular work center, location or room and combine the notifications that should be processed together.
Example
Every three weeks a specialist comes to your company, who requires a toolbox for some maintenance activities.
Previously, the specialist received several orders, in which the activities to be performed were described. The organization and
completion confirmation were unnecessarily repeated in the individual orders.
You can use the worklist for planned maintenance to combine all relevant notifications into one
order. For example, you can select the notifications for this order according to work center. The
specialist receives only one order, thereby saving paper. The
processing and completion confirmation of the activities performed have been simplified considerably.
Process
1. You create separate maintenance plans with maintenance call object
"notification" for all the planned activities in your company. Enter a
task list in the maintenance item for the maintenance plan, in which the activities are described exactly.
2. During maintenance plan scheduling, the system generates a notification
for the due date of the maintenance calls for each maintenance item for a maintenance plan.
3. If you call up list editing for notifications in change mode, you can
display the notifications generated and select the notifications, which should be combined into one order ("worklist").
4. When an order is created from the list editing function, the selected
notifications are combined into one order according to the following criteria:
- The individual notifications are listed in the order object list. It is
still clear from which maintenance plan a notification originates.
- If you have specified a task list in a maintenance item for a
maintenance plan, the operations for the task list are copied into the
order. The sequence of operations corresponds to the sequence of notifications in the object list.
5. You can print and process the order with all operations.
6. You confirm the completed activities to the order.