In this step, you specify the reduction strategy to be used when the reduction measures are carried out on operations. Scheduling reduces the lead_time automatically if the basic dates given are not adhered to, that is if the scheduled dates lie outside the basic dates.
In this work step, you also define the reduction levels. The reduction takes place level by level no further than the level that you have specified in the control parameters.
You can specify a reduction strategy in every
operation.
The SAP system carried out reduction step by step no further than the reduction level specified in the scheduling parameters.
The order/network is rescheduled after every reduction level. To improve performance we recommend that you keep the number of reduction steps to a minimum.
The reduction levels are predefined in the SAP standard package.