Valuation of Material Components 
Use
The system valuates material components in valuated stock according to the strategy below.
During the first goods receipt, the system saves a standard price in the individual stock segment for a material, plant and WBS element. Afterwards you can only change this price by using Transaction MR21. If the standard price was determined during the first goods receipt, for example by using User-Exit COPCP002, it is not determined during further goods receipts.
In the case of materials with moving average prices, the system also determines the moving average price for each goods movement.

You cannot create segments with Transaction MR21.
Features
For goods movements the system valuates material components in valuated stock according to the following strategy.
The strategy is determined in the above sequence in the following cases:

You can use unit costing for a material component in a network to define a price for valuation. Since only one standard price is saved for each combination of material plant and WBS element, it is pointless to execute another unit costing for the same combination, for example for another network. The system always uses the value it determined first.