Production
Order Phases
Production orders go through different phases
that follow on from one another. These phases are represented by the
production order status:
1. First,
production orders are created (CRTD).
2. Production
orders are released (REL).
3. Shop floor
papers are printed (PRT).
4. Production
orders are executed. The quantities produced, the activities and the dates are
continually confirmed (PCNF).
5. Eventually,
final confirmation takes place (CNF).
6. The
production orders are technically completed (TECO).
7. Finally, the
production orders are flagged for deletion (DLFL).
A workflow can be started when a production
order is created. It continually informs the MRP controller about the phase in
which the production order is currently to be found.
Note that in this scenario a lot of work items
may be created. Therefore, if there are a lot of production orders in your
active system, you should not use this scenario.
If the existing scenario does not meet your
requirements, you can use it as a template for creating your own
scenario.
Activities
1. Maintain
processor assignment
Link the standard
tasks TS20000634, TS20000636, TS20000637, TS20000638, TS0000639, TS20000640
with your possible processors.
2. Link MRP
controllers with the organizational management
If you only want the
MRP controller who is responsible for the production order to receive a work
item, rather than all possible processors assigned to the standard tasks, link
the MRP controller (organizational object type T024D) with the SAP
organizational management.
3. Activate
event linkage
Activate event
linkage between the workflow template WS20000387 and the event
BUS2005.Created.
4. Ensure event
creation via status management
Enter the following
for status object type ORH and for business object type
BUS2005:
- Event Created, status
restrictions SysStatus = I0001 CRTD
- Event Released, status
restrictions SysStatus = I0002 REL
- Event Printed, status
restrictions SysStatus = I0007 PRT
- Event Confirmed, status
restrictions SysStatus = I0010 PCNF
- Event FinallyConfirmed,
status restrictions SysStatus = I0009 CNF
- Event TechnicallyCompleted,
status restrictions SysStatus = I0045 TECO
- Event Deleted, status
restrictions SysStatus = I0076 DLFL
Further
Notes
For more information, for example, about how to
inform the production scheduler instead of the MRP controller, refer to the
component BC - Basis by choosing Business Management
-> SAP Business Workflow -> Reference Documentation -> Workflow
Scenarios in Applications -> Production Planning and Control ->
Production Order Phases (PP-SFC).