Performing Primary Cost Planning and Revenue Planning 

You access Primary Cost and Revenue Type Planning:

Procedure

  1. Choose Planning ® Set planner profile and enter the following for planning:
  1. Choose
  1. In the period screen, you can plan each internal order across cost elements for the periods of a fiscal year.
  2. In the overview screen, you can plan each internal order per period by cost elements.
  3. The structure of this screen depends on the combination of planning objects you entered on the initial screen. If, for example, you enter an individual internal order and an individual cost element, then the system only displays these two objects.
  4. Save your planning values.

Results

You can obtain the cost element planning value by doing the following:

Call up overall planning for your order group and choose Views ® Cost element planning In Plan total, the cost element planning value appears in the right-hand column, and is marked with a K.