The Production program position of investment program INVEST/2000 is assigned to a project that has actual values and a commitment.
You carry the commitment forward to the new fiscal year. In the next step, you carry forward the unused budget of the project (that is, the budget minus the actuals that were posted). As a result, the investment measure has a higher budget in fiscal year 2001 than was originally approved for fiscal year 2001 in the investment program.
By means of the budget carryforward in investment program function, the unused budget is transferred to the next fiscal year (that is, the budget minus the actuals that were posted). Now the budget on the measure does not exceed the budget on the investment program position to which it belongs.