Creating Report Shipping Orders Manually 
Prerequisites
In report management, the status of the report must be changed to RE (Released) (see
Report Management).The report has the report type Material safety data sheet.
In the R/3 material master, you have created the material or the default material for which you want to send the report.
Procedure
The initial Report Information System screen appears:
The report information system appears.

To send reports, you must be in the material view. If necessary, choose Utilities ® Toggle view ® Material view. If no material has been assigned to the substance of a substance report, the R/3 System displays the default material that you assigned by choosing Utilities ® Change default mat. You can carry out shipping using the default material, or you can choose Utilities ® Change default mat. to assign a different material.
The Report shipping: enter parameters dialog box appears.
Recipient parameters |
Choose between
|
Procedure parameters |
Choose between
When shipping a document manually by fax, you must enter the fax machine as the output device. |
Additional parameters |
Decide if this shipping order is relevant for subsequent shipping. The indicator is set as default if you have set it in the IMG activity Check shipping reasons. |
The shipping process is started.
Result
The report shipping order that has been manually generated is given the starting status, depending on the process parameters chosen and the initial status that you defined in the IMG activity Check shipping reasons.

The process parameters that you selected manually override the process type that you defined in the IMG activity Check shipping reasons.
If the following settings have been made: |
The report shipping order is given the status |
Process parameter: In the background: Initial status {0 (Created) |
SW (Start of work) You must accept this status manually in order to reset the status of the shipping order to RE (Released). |
Process parameter: In the background: Initial status {1 (Released) |
RE (Released) Report RCVDDISP starts the report shipping order at a defined time. Report RCVDEVEN then calls the user exit EHS_CHECK (see Checking Report Shipping Orders). |
Process parameter: Immediately: Initial status AA or RE. |
RE (Released) Report RCVDEVEN immediately calls the user exit EHS_CHECK. |
See also:
Report Shipping Status Network