Carrying Out Resource Leveling 

  1. From a single-level screen in the planning table, choose Views ® Capacity situation and either Detailed planning, Rate-based planning, or Rough-cut planning ® Show.
  2. The split planning table appears. In the lower section of the screen, you see the available capacity, capacity requirements, and capacity load for each work center used in production and each capacity category.

    In the event of an error, check that the prerequisites for resource leveling have been fulfilled (see How to Carry Out Resource Leveling).

  3. Adjust the planning data in the upper section of the screen until you arrive at a plan which is also acceptable from the point of view of capacity.
  4. To view the source of the capacity requirements in a period, place your cursor on them and choose Views ® Capacity situation ® Pegged requirements.
  5. If desired, branch into a standard analysis of other resources with Views ® Capacity situation ® Rough-cut planning and either ® Materials/PRT or Costs.

 