Creating the Internal Order with Order Manager and Planning Costs 

Prerequisites

The planning form Internal order exists in the system.

Procedure

  1. Call up the transaction as follows:

Menu Path

Accounting ® Controlling ® Internal Orders Master Data ® Order Manager

Transaction Code

KO04

  1. If you are requested to Set the controlling area make the following entry and choose :
  2. Field

    Data

    Controlling area

    1000

  3. Choose .
  4. The dialog box Create internal order appears.

  5. Enter the Order type 0652, then choose .
  6. Enter the Short text IT Implementation.
  7. On the Assignments tab page, enter the following data:

Field

Data

Company code

1000

Business area

1000

Plant

1000

Object class

Investment

Profit center

1400

  1. Choose .
  2. The dialog box Create Cost Estimate appears with the predefined costing variant PC02.

  3. Choose Create cost estimate.
  4. The screen Internal order: IT Implementation: Change: Easy Cost Planning appears.

  5. Choose Choose planning form in the work area.
  6. The dialog box Create cost estimate appears.

  7. Enter Internal order as the Name, and choose .
  8. If there are several planning forms with this name, then select Costing model IA001.

  9. Choose .
  10. The initial entry screen is displayed. IT Implementation is selected as the Order type.

  11. Confirm this selection by choosing Confirm.
  12. In the costing structure the nodes IT: Concept, IT: Implementation and IT: Preparation are inserted to structure your planning. In the following you create a separate cost estimate for each of these nodes:

  13. Click on the node IT: Concept.
  14. In the work area the planning form entry screen is displayed.

  15. Enter the following data:

Field

Data

Working hours

100

Additional costs

13400

  1. Choose Confirm.

Depending on the data you entered the system determines the costing items using the planning form and displays them in the costing structure.

If you would like an overview of the meaning of the symbol legends displayed in the costing structure, choose in the application toolbar. If you want to see the aggregate costs, either change the column width as appropriate in the screen area Costing structure, or increase the screen area .

  1. Proceed in the same way for the other nodes, making the following entries:

Node

Field

Data

IT: Implementation

Internal working hours.

130

 

Number of licenses

50

IT: Preparation

Internal working hours

90

  1. Choose Confirm in each case.
  2. Choose .

You return to the Order Manager.

  1. Choose .
  2. Remain on this screen.

Result

You have created the internal order and planned the costs. You can now submit your planning for approval.

Dispatching the Order for Approval and Release