Maintaining Scheduling Parameters and Saving Maintenance Plan
Use
The scheduling parameters define when and for how long maintenance calls are created for the maintenance plan. They also determine when in the maintenance cycle maintenance call objects should be created.
Procedure
Field |
Data |
Description |
Call horizon |
90 |
The call horizon determines that a maintenance order is created when 90% of the maintenance cycle has elapsed. |
Scheduling period |
365 |
Maintenance dates are calculated for the entire year (365 days). |
Start of cycle |
Today’s date minus three months |
Because you have already entered the start date, the first maintenance appointment is already due and you can call it up immediately.
Note the number of the maintenance plan.
Result
You have created maintenance calls (for a period of 365 days) for the maintenance plan. For a cycle lasting three months, a maintenance order is created after 90 days x 90% = 81 days.