Settings in the Standard System 

In the standard system there are two strategy groups with corresponding main strategies:

Determining the requirements class for a sales document item

Assembly Processing without Project (Strategy 83)

The strategy and not the item category determines the requirements type. Strategy 83 leads to requirements type KMNP, which in turn leads to requirement class 202. This requirement class has the following settings:

Assembly Processing with Project (Strategy 85)

The strategy and not the item category determines the requirements type. Strategy 85 leads to requirements type KMPN, which in turns leads to requirement class 212. This requirement class has the following settings:

Summary

Strategy

Requirements class

Account assignment category

Consumption posting

Account assignment object

Network type

83

202

E

E (sales order)

Sales order

Header assigned (PS05)

85

212

D

P (project)

Project

Activity assigned (PS04)